Reduced welding times

 

Reduced welding times for faser composite pipes 

With our TechNews 8/2019 from December 18, 2019, we had already informed you about the amendment of the guideline of the German Association for Welding and Related Processes (DVS) DVS 2207-11 (title: Welding of thermoplastics – heating element welding of pipes, pipeline parts and PP sheets). When the version was updated from 2008 to 2017, significantly reduced times were defined for both the heating and cooling times. In addition to the information from December 18, 2019, we can now confirm that the reduced welding times of the 2017 version can also be applied without restriction to faser composite pipes.

 